I am putting up a 3500 sq ft workshop (16 ft walls) on a mono poured concrete pad (16″ deep on edge …. 6″ slab … 24″ rebar meshed).
We did not put any anchor bolts in it (poured a few years ago).
What is the best way to anchor the sill?
I was originally going with 1/2″ threaded bar epoxied in 6″ deep.
Some of framers are saying they want to use anchors.
I have used a few different types … I have also pulled a few out way to easily!
I did some homework ….way tooooo many choices … maybe sleeve or wedge?
Maybe sleeve or wedge with a shot of epoxy first in the hole?
Not sure which way to go … any advice?
Thanks … Mike
Replies
The best specs are for Titen HD, that simply screw into a hole in the concrete. Believe it or not.
https://www.strongtie.com/mechanicalanchors_mechanicalanchoringproducts/thd_anchor/p/titen-hd