I have a 28×40 garage slab I poured 2 weeks ago and was unable to cut control jionts in it due to a family emergency.Should I try to cut them now or not ? Also should the cuts go all the way to the edge?
Discussion Forum
Discussion Forum
Up Next
Video Shorts
Featured Story
In this FHB Podcast Segment, the team chats about the best way to build a paintable surface over an old wall.
Featured Video
A Modern California Home Wrapped in Rockwool Insulation for Energy Efficiency and Fire ResistanceRelated Stories
Highlights
"I have learned so much thanks to the searchable articles on the FHB website. I can confidently say that I expect to be a life-long subscriber." - M.K.
Replies
control joints
I'm no expert on the subject, but it is my understanding that if you don't cut them as soon a possible, it does not do any good to cut them.
Some time back, I found a web site that was pretty thorough on the subject. You might try http://www.concretenetwork.com
I'm thinking the contrary
Concrete will crack, you just help it decide to figure where.
Cutting them now can't hurt and quite possibly might help down the road.
Things such as what's in the slab as far as reinforcement might help also. Going all the way that you can is a good idea, as if it does crack there, it'll then go toward the edge or corner (if inside corner).
Any posts on footings in the slab?
concrete
It is a monolithic slab with a18x18 inch footing it has wire mesh in the slab section and half inch rebar in the footing section and is sitting on 12 inches of compacted1inch roadbase , also no post
what harm could it do?
On the other hand, what good would it do? The idea is to control where and how the cracks will occur. If you wait to long, you lose this control. You may saw the control joints later, but the concrete may have decided where it is going to crack and you may or may not locate your control at these points. Now you may have cracks where there or no control joints and control joints where there are no cracks. :>)
This is discussed in the link that I posted above.
Link
Could you provide another link to the discussion?
Misc.
Et TOO Calvin. :>)
The thing is, you have no idea whether significant cracks may already have developed.
One thing the OP can do is flood the area with water, then wait for it to dry. The cracks will remain dark after the bulk of the water has dried out. This will let him judge the degree to which cracking may already have occurred.
oops
The link you posted is to the general site, maybe you could post one on the "too late to cut" subject. I hate hunting around.......especially on this borrowed computer.
thanks
Calvin. Yeah, there is almost more info. than you want at the site. I went through it a found the info. Take a little doing, but try this.
Go to the web site then click on the following:
concrete driveways
Concret driveway construction practices
correctly placed joints
Then click on the high lighted "control joints"
Hope this helps.
There may be a better way of doing this, but I know more about pouring concrete than operating a computer.
Bruce
I suspect it is done now or not going to be. I would have cut them, like mike, same reasoning. How soon it cracks depends on a LOT of variables that none of us here knows
I could not find that article by that means, ran a term search and got lots listed. Can youchoose it from one of these?
http://www.concretenetwork.com/search.aspx?q=%22control+joints%22&x=25&y=9
Or, like I suggested, flood it with water to see what, if any, cracks have developed.