FHB Logo Facebook LinkedIn Email Pinterest Twitter X Instagram Tiktok YouTube Plus Icon Close Icon Navigation Search Icon Navigation Search Icon Arrow Down Icon Video Guide Icon Article Guide Icon Modal Close Icon Guide Search Icon Skip to content
Subscribe
Log In
  • How-To
  • Design
  • Tools & Materials
  • Restoration
  • Videos
  • Blogs
  • Forum
  • Magazine
  • Members
  • FHB House
  • Podcast
Log In

Discussion Forum

Discussion Forum

Contract Penalty clause and the law

| Posted in General Discussion on December 11, 2003 03:40am

Years ago I was told by a builder that I was employed with (former architect): If a contract states that a contractor is to be penalized every day work is unfinished beyond a set completion date, the contractor, by law, is entitled to a bonus, equal to the penalty, for days the project is finished ahead of the completion date.

 

I understand that the contract doesn’t have to specify the bonus it’s just implied with the penalty clause.

 

Now I don’t have access to my states laws to confirm this, but would like to know if it’s true and is it common through all the states?

 

I’m in Michigan by the way.

Scott R.
Reply
  • X
  • facebook
  • linkedin
  • pinterest
  • email
  • add to favorites Log in or Sign up to save your favorite articles

Replies

  1. caseyr | Dec 11, 2003 04:30am | #1

    I'm not a lawyer, and it has been several decades since I had a course on contracts, but I would seriously doubt that in most (all?) states you would be entitled to a bonus unless it was spelled out in the contract. 

  2. VaTom | Dec 11, 2003 06:18am | #2

    Not in Virginia.  Sounds like your builder was doing some wishful dreaming.

    PAHS Designer/Builder- Bury it!

  3. MarkMc | Dec 11, 2003 06:35am | #3

    Agreed with above.

    If it ain't in the contract, it hard to argue that an assumption is contractual.

    Now, just for perspective, whenever I've had a client suggest a penalty clause, I've always been agreeable if they match the penalty with a early completion bonus.

    Not once has the subject seen further discussion. Funny how that works.

    1. DavidThomas | Dec 12, 2003 12:08am | #23

      McDonnell: "Now, just for perspective, whenever I've had a client suggest a penalty clause, I've always been agreeable if they match the penalty with a early completion bonus.  Not once has the subject seen further discussion. Funny how that works."

      I'm still a contractor of sorts (but only on engineering projects these days), but here's a perspective from the other side of the fence:

      I've advised several friends about remodeling contracts.  Rather than ask for a bid price with a $100/day penalty clause (or propose a penalty clause after the bid is presented), I suggest the homeowner do the following.

      The bid is $20,000.  Has to be done in 16 weeks (baby on the way).  When getting the bid, HO asks GC, "How long to finish?  Time is important to us."  GC says 6 weeks.  HO proposes, "How about a bonus/penalty clause of $500 a week if early/late for completion at 10 weeks? (note the longer time)!  Finish on time and you get $22,000."

      That's $2,000 free money to GC for on-time.  $3,000-4,000 of free money if he really cranks.  He accepted.  But project wasn't on time.   Went over by 3 weeks.   Benefits to HO: They saved $1,500.  And, since GC knew he was losing money each week, their project got the crew while others' projects languished.

      But I think it was a balanced contract, with both a stick and carrot.  The homeowners would have been happy to pay the bonus and were thankful I insisted on the stick (I was the bank).

      David Thomas   Overlooking Cook Inlet in Kenai, Alaska

      1. MarkMc | Dec 12, 2003 03:38am | #26

        Sounds reasonable David.

        The bottom line on inserting language that calls for any penalty/bonus is it turns the contract into a "time is the essence" agreement.

        Deadly to someone producing a product with raw materials that are delivered to a private property, usually at the mercy of the weather, acts of God, ect.

        Deadly to a Building Contractor. Not deadly to a defense contractor building cruise missles in a climate controled factory.

        Never, never be tempted to accept an early completion clause. If there is a product failure, an accident, anything that would appear to a jury that the reason for the "tragedy" was becaused you rushed for the sake of profit. Deadly.

        1. DavidThomas | Dec 12, 2003 06:30am | #27

          "would appear to a jury"

          And therein lies another advantage of a performance/penalty clause or an agreed upon liquidated damages amount. At least there's nothing to go to the jury regarding schedule. You've already decided what the answer will be.

          But I agree that the temptation/perception of doing bad work to make the date is increased. Obviously, only a well-specified job could be done with a performance clause. And independent milestones for completion (e.g. city inspector sign-offs). Design-as-we-go jobs wouldn't work.

          I've made a ton of extra money on some performance clauses. And sometimes lose some. But in general they make the job more interesting to me.David Thomas   Overlooking Cook Inlet in Kenai, Alaska

  4. User avater
    rjw | Dec 11, 2003 06:52am | #4

    Not in PA law or NY law or common law.

    Sounds like one of those wishful thinkin' kind of things to me.

    _______________________


    Tool Donations Sought

    I'm matching tool donors to a church mission to Haiti - we're shipping a bus converted to a medical facility in January (we hope) and can fill it with clothes, tools and all sorts of stuff needed in that poorest of all countries. A few hand tools or power tools can provide a livelihood for an otherwise destitute family. Please email me if you have tools to donate.

    1. User avater
      BillHartmann | Dec 11, 2003 07:35am | #5

      I thought that it was sorta of the oposite.

      That penalty clause was not enforcable unless there was a corresponding bonus clause.

      1. sdr25 | Dec 11, 2003 03:46pm | #13

        My memory is certainly fading after all these years, but Bill Hartmann’s response sounds more plausible and may be actually what my employer was telling me.

         

        “That penalty clause was not enforceable unless there was a corresponding bonus clause”.

        Any thoughts on this? 

         

        McDonnell quote “Now, just for perspective, whenever I've had a client suggest a penalty clause, I've always been agreeable if they match the penalty with a early completion bonus.

        Not once has the subject seen further discussion. Funny how that works.”

        Been their done that and it is quite humorous how nobody pursues the matter any further.

         Scott R.

        1. Piffin | Dec 11, 2003 04:16pm | #14

          Well, to me, Bill Hartman's reply sounded like what would be fair, and nice, and right, but I thought you were pursuing answers about what is the law.

          Law is very specific and not always fair and nice and right, in line with our dreams. if you want a specific item in your contract, put it in instead of playing guessing games. If you are going to depend on the answer to this question, get the answer from your attorney. At least you can kick him in the seat of his pants if he advises you wrong..

          Excellence is its own reward!

          1. sdr25 | Dec 11, 2003 11:20pm | #20

            Well piffin by that condescending response guess I need to clarify that I did not post the question to depend on responses as genuine legal counsel, and your insinuation that I am dimwitted enough to do is eminent.

             

            The topic of a penalty clause came up in discussion so thought I would defer to the brain trust of Breaktime to see if what I heard many years ago COULD be true. Having an attorney research the correct answer would certainly provide a definitive answer but I don’t have the funds to ask just out of curiosity questions at $200 an hour.

             

            I highly respect the individual from whom this "vague" information came, so from my perspective the probability of it being true was fairly good, hence inquiring specifically regarding the law. As I alluded to in a previous post, what I was told and what I remember could be two different things. Just a harmless question... Relax!Scott R.

          2. Piffin | Dec 11, 2003 11:52pm | #21

            Don't know what I wrote that came off as condecending, but my impression of your comments was that you appeared to be looking for the answer you were looking for and not any brain trust info. You were choosing to lean toward believing the one vague comment that appeared to agree with you mentor in opposition to all the other comments shared in answer to your query.

            I was just trying to correct your prejudicial thinking.

            Sorry to have helped..

            Excellence is its own reward!

          3. User avater
            rjw | Dec 11, 2003 11:52pm | #22

            Scott - interesting - I didn't see any condescension in his answer - just plain old common sense.

            _______________________

            Tool Donations Sought

            I'm matching tool donors to a church mission to Haiti - we're shipping a bus converted to a medical facility in January (we hope) and can fill it with clothes, tools and all sorts of stuff needed in that poorest of all countries. A few hand tools or power tools can provide a livelihood for an otherwise destitute family. Please email me if you have tools to donate.

          4. DavidThomas | Dec 12, 2003 12:16am | #24

            Scott:  I can imagine how you might have seen Piffin's post in a negative light, but I've probably read a few thousand more of his posts than you have.  I'm pretty sure he was just trying to point out the consensus of most people here is:

            Sorry, unless they had a gun to your head at the signing, a penalty clause would be enforceable with or without a bonus clause.   

            That consensus, of course, coming from a bunch of non-lawyers (who however have been around the block a few times) and a few lawyer wanna-bes.  As you knew.

            P.S. You must live in a small town like I do if lawyers are only $200/hour!

            On that point, for your enjoyment: http://www.dilbert.com/comics/dilbert/archive/dilbert-20031126.html

            David Thomas   Overlooking Cook Inlet in Kenai, Alaska

          5. Piffin | Dec 12, 2003 01:05am | #25

            OK Guys, I re-read mine again and I see that I wrote with some brevity (for me) and maybe came across as short in my concise choice of words. Today, I am winding down from an all-nighter getting that slab poured. The weather finally came off just right and the temps ran up around 40°F or so. Tucked her in under the blankets and got home by 4AM again.

            So I may have been less than tacvtfull and careful in my choice of words.

            Tho I will stand behind my impression that Scott wanted to hear more opinions that agreed with his mentor.

            Peace, Scott?.

            Excellence is its own reward!

          6. sdr25 | Dec 15, 2003 05:48pm | #29

            Piffin, no harm no foul.

             

            I’ve come to respect your input on this message board; It was the “playing guessing games” that was the trigger. J

             

            As responses were coming in I had thoughts of contacting my mentor, not only to clarify the topic from his perspective but also to hear about the eccentric project he and his crew were currently tackling. We’ve kept in contact over the years, mostly me calling him to get an opinion on tough situation. The timing is right for me to “check in” and get the latest info. His incredible knack for design, use of materials and incorporating unusual construction methods was something I would question about for what could have easily gone on for hours. There was much information from him I did actually take to the bank, so I would be surprised if a kernel of truth doesn’t exist regarding my understanding of this topic. Keep in mind the fault of the facts likely does not exist with the source just my representation from the source.

             

            However this will forever remain a mystery. The day following my last response in this thread, I got the very saddening news that we would be laying my friend to rest on Saturday.

             

             

            Terry Johnson, Ar-Tek Construction 1943-2003

          7. johnAwalker | Dec 15, 2003 10:57pm | #30

            I often sign contracts with a liq. damages clause. They are usually $70.00 t0 a $100.00 a day over completion date (contract value $200k - $400k)

            They are simply an incentive to stop wayward builders from dragging out a project for whatever reason.

            If I have delays, variations, bad weather etc. I write to the Architect and request an extension of time. I never been penalized and don't expect to be even when  a few weeks or month over time. The Architects don't what to enforce it I think its just peace of mind for the client. 

            I would never sign a contract with a penalty clause where no third party is administrating the contract, you would be asking for trouble.

            cheers johnhttp://www.johnwalkerbuilders.com

      2. User avater
        rjw | Dec 11, 2003 04:18pm | #15

        I confess I'm hazy on this stuff now, but as I recall, "penalty" clauses are often considered unenforceable, at least to the extent they are considered "punishment" as opposed to compensation.

        A basic principle of contract law in the US and common-law countries is that the parties are free to set the terms of the contract within the overall constraints of public policy.

        Think of a contract as a private law between the two parties.

        So long as each of the parties have at least some bargaining power (i.e., not a take it or leave it sort of situation - or mega corp v consumer) the courts will give them wide leeway to decide on the terms of the "law," that is, the contract, between them.

        Also, if I remember correctly, those "penalty clauses" are technically called "liquidated damages" clauses - and there is a set of "rules" for distinguishing enforceable liquidated damages clause from unenforceable penalty clauses.

        As for the quid pro quo concept - that is a basic requirement for contracts to be found enforceable - aka "consideration." But "consideration doesn't have to be proportionate - as long as each side gets something out of the deal ("In consideration of $1.00, one dollar, receipt of which is hereby acknowledged" - a "famous" consideration weasel) the contract will be "supported by adequate consideration."

        But that's just the contract as a whole - there doesn't have to be an "internal balance" of the parts.

        I still think that the original idea floated was someone's wishful thinking - about as close to the ways things are really done as if I were to design a nuclear sub.

        _______________________

        Tool Donations Sought

        I'm matching tool donors to a church mission to Haiti - we're shipping a bus converted to a medical facility in January (we hope) and can fill it with clothes, tools and all sorts of stuff needed in that poorest of all countries. A few hand tools or power tools can provide a livelihood for an otherwise destitute family. Please email me if you have tools to donate.

        1. User avater
          bobl | Dec 11, 2003 04:36pm | #16

          As I remember liquidated damages they have to be tied to real loss.

          I put them in a couple of contracts (gov't) but had to justify the damage figure to our lawyers before they would put it inbobl          Volo, non valeo

          1. User avater
            rjw | Dec 11, 2003 05:42pm | #17

            >>As I remember liquidated damages they have to be tied to real loss.

            I think you're right on that, although there is a wrinkle on that.

            One of the other rules I remember (at least from a CA case -which I remember because I got quizzed on it in class by one of the greatest of contracts prof's on this issue in Contracts 1 - Grant Gilmore - kind of like a physics student getting quizzed on relativity by Einstein {G}) is that a liquidated damages clause will only be enforceable if, prior to entering into the contract, the parties would have been unable to estimate what the extent of potential damages might be in the event of a breach.

            Courts recognize that one aspect of a contractual relationship is to anticipate and allocate amd manage risk.

            Because a liquidated damages clause doesn't tie the damages to the actual amount or extent of loss, courts will allow them only in narrow circumstances.

            _______________________

            Tool Donations Sought

            I'm matching tool donors to a church mission to Haiti - we're shipping a bus converted to a medical facility in January (we hope) and can fill it with clothes, tools and all sorts of stuff needed in that poorest of all countries. A few hand tools or power tools can provide a livelihood for an otherwise destitute family. Please email me if you have tools to donate.

          2. User avater
            bobl | Dec 11, 2003 06:19pm | #18

            lawyers

            the clause we called liquidated damages was based on an estimate of what actual damages might be, as oppssed to determining actual costs after the fact.

            one contract in particular i remember was a system for in proccesing supplies as they were delivered.  had what we called a liquidated damage if the system wasn't repaired within a set time.  the estimate was based on the gov't's cost of having to pay for trucks being lined up waiting to unload, and using the normal rate of trucks arriving at the facility.

            this sounds like something u posted as not being a liquidated damage.

            but that's what we called it and the type of thing we had to do to come up with a figure.

            the lawyers were part of calling liquidated.bobl          Volo, non valeo

          3. User avater
            rjw | Dec 11, 2003 06:51pm | #19

            One think to keep in mind on stuff like this is there are variations from state to state -some big, some small and insiginificant, some small and very significant!

            _______________________

            Tool Donations Sought

            I'm matching tool donors to a church mission to Haiti - we're shipping a bus converted to a medical facility in January (we hope) and can fill it with clothes, tools and all sorts of stuff needed in that poorest of all countries. A few hand tools or power tools can provide a livelihood for an otherwise destitute family. Please email me if you have tools to donate.

          4. RonnyK | Dec 15, 2003 11:01pm | #31

            As a lawyer, I find the possibility of such a law existing to be unlikely.  Granted, state law determines contract interpretation and I cannot possibly verify every state's contract law, but a general proposition that states the law will read into a contract penalty provision the exact opposite proposition (i.e. a bonus) would definitely not be the norm (and is not the law in the states in which I practice).

            One would have to wonder, if by the same logic, a contract that provides for a bonus would be interpreted to levy a penalty should the contract not be completed on schedule?

  5. BungalowJeff | Dec 11, 2003 08:01am | #6

    The others are correct. This is just some wishful thinking. As a matter of fact, I just finished a project with a $150,000/day late clause (for substantial completion). The contractor would only have gotten an "atta boy!" if he had actually been early.

    ...that's not a mistake, it's rustic

    1. toast953 | Dec 11, 2003 08:14am | #7

      "I just finished a project with a $150,000/day late "  Please, do tell,, what type project was this one???. Thanks Jim J

      1. BungalowJeff | Dec 11, 2003 08:38am | #8

        Well, it was no Fine Home. More like a big hole. This was to construct an access shaft next to an existing tunnel. 70' deep under 60' of groundwater, with two active subways and an elevated rail line nearby to make things fun. Slurry walls, 400 ton tiebacks, rock blasting, and lot's of chemical grouting. The penalties are steep because the access shaft is on the critical path for follow on rock tunnelling contracts (TBM, drill-and-blast, and road header) that will run through the existing tunnel into Manhattan and haul the muck back into Queens.

        I just got the go ahead to get the adjacent contract ready. This one will create a bigger hole for a future tunnel with a substation and vent plant.  This big open-cut will first be used to launch soft-ground tunnel boring machines. The contract will also underpin a subway, an elevated transit line, and a busy truck route in one 100-foot segment. We may be using ground freezing to cutoff the groundwater in this one. This contract is also on the critical path, so similar delay clauses will be included....that's not a mistake, it's rustic

        1. toast953 | Dec 12, 2003 08:52am | #28

          Wow,,yep, if I had to work with water 10' above my head, I'd go home to my bungalow too. thanks, Jim J

  6. specarch | Dec 11, 2003 09:44am | #9

    No! I don’t think there’s a law that states such a requirement.  This would only be true if it’s explicitly stipulated in the contract; condition spelled out and agreed to by both parties before commencement of work.  When there’s is no such stipulation and the contractor defaults, well that’s when the Lawyers or Arbitrators get called in.

    The bonuses do not have to be equal to the penalty either. Usually a percentage over the losses or a fixed daily amount is used by the owner as a penalty. At the same time the bonus can be the same, more than the penalty or none at all, there is no rule. It’s all how it is written. A bonus is used to give the contractor an incentive to complete the project on time.

    This sort of contract is generally not used, and when it is, it’s usually in bigger projects where the owner need the project completed at a certain time because of personal gain,  potential losses or agreements to another parties where they have penalties or losses.

    Contacts of this nature are usually completed on standard AIA (American Institute of Architects) documents; edited and reviewed by each parties council.

    (You may want to look at a copy of AIA documents A101, A107 or A111 and all three in conjunction with General Conditions A201)

    Keep in mind, if all the Contractors where required to pay for each time they don’t complete a project on time, there would not be too many contractors around.



    Edited 12/11/2003 2:25:52 AM ET by specarch

  7. mikerooney | Dec 11, 2003 11:49am | #10

    A friend of mine told me that once, a long, long time ago, somebody actually finished a job ahead of schedule.

    1. Piffin | Dec 11, 2003 12:57pm | #11

      That is true.

      It was Me.

      and it was a LONG time ago.

      ;).

      Excellence is its own reward!

      1. UncleDunc | Dec 11, 2003 01:24pm | #12

        Since we're now quoting scripture here: Genesis 2:1-2

Log in or create an account to post a comment.

Sign up Log in

Become a member and get full access to FineHomebuilding.com

Video Shorts

Categories

  • Business
  • Code Questions
  • Construction Techniques
  • Energy, Heating & Insulation
  • General Discussion
  • Help/Work Wanted
  • Photo Gallery
  • Reader Classified
  • Tools for Home Building

Discussion Forum

Recent Posts and Replies

  • |
  • |
  • |
  • |
  • |
  • |
View More Create Post

Up Next

Video Shorts

Featured Story

Vintage Sash Windows Get an Energy-Efficient Upgrade

Low-e storm panels improve the energy efficiency of these old sash windows without changing their classic look.

Featured Video

How to Install Exterior Window Trim

Learn how to measure, cut, and build window casing made of cellular PVC, solid wood, poly-ash boards, or any common molding material. Plus, get tips for a clean and solid installation.

Related Stories

  • Old House Air-Sealing Basics
  • A Drip-Free, Through-Window Heat Pump
  • Insulation for Homes in the Wildland Urban Interface
  • An Impressive Air-to-Water Heat Pump

Highlights

Fine Homebuilding All Access
Fine Homebuilding Podcast
Tool Tech
Plus, get an extra 20% off with code GIFT20

"I have learned so much thanks to the searchable articles on the FHB website. I can confidently say that I expect to be a life-long subscriber." - M.K.

Get home building tips, offers, and expert advice in your inbox

Signing you up...

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
See all newsletters
See all newsletters

Fine Homebuilding Magazine

  • Issue 332 - July 2025
    • Custom Built-ins With Job-Site Tools
    • Fight House Fires Through Design
    • Making the Move to Multifamily
  • Issue 331 - June 2025
    • A More Resilient Roof
    • Tool Test: You Need a Drywall Sander
    • Ducted vs. Ductless Heat Pumps
  • Issue 330 - April/May 2025
    • Deck Details for Durability
    • FAQs on HPWHs
    • 10 Tips for a Long-Lasting Paint Job
  • Old House Journal – August 2025
    • Designing the Perfect Garden Gate
    • Old House Air-Sealing Basics
  • Issue 329 - Feb/Mar 2025
    • Smart Foundation for a Small Addition
    • A Kominka Comes West
    • Making Small Kitchens Work

Fine Home Building

Newsletter Sign-up

  • Fine Homebuilding

    Home building tips, offers, and expert advice in your inbox.

  • Green Building Advisor

    Building science and energy efficiency advice, plus special offers, in your inbox.

  • Old House Journal

    Repair, renovation, and restoration tips, plus special offers, in your inbox.

Signing you up...

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
See all newsletters

Follow

  • Fine Homebuilding

    Dig into cutting-edge approaches and decades of proven solutions with total access to our experts and tradespeople.

    Start Free Trial Now
    • Facebook
    • Instagram
    • X
    • LinkedIn
  • GBA Prime

    Get instant access to the latest developments in green building, research, and reports from the field.

    Start Free Trial Now
    • Facebook
    • YouTube
  • Old House Journal

    Learn how to restore, repair, update, and decorate your home.

    Subscribe Now
    • Facebook
    • Instagram
    • X
  • Fine Homebuilding

    Dig into cutting-edge approaches and decades of proven solutions with total access to our experts and tradespeople.

    Start Free Trial Now
    • Facebook
    • Instagram
    • X
    • LinkedIn
  • GBA Prime

    Get instant access to the latest developments in green building, research, and reports from the field.

    Start Free Trial Now
    • Facebook
    • YouTube
  • Old House Journal

    Learn how to restore, repair, update, and decorate your home.

    Subscribe Now
    • Facebook
    • Instagram
    • X

Membership & Magazine

  • Online Archive
  • Start Free Trial
  • Magazine Subscription
  • Magazine Renewal
  • Gift a Subscription
  • Customer Support
  • Privacy Preferences
  • About
  • Contact
  • Advertise
  • Careers
  • Terms of Use
  • Site Map
  • Do not sell or share my information
  • Privacy Policy
  • Accessibility
  • California Privacy Rights

© 2025 Active Interest Media. All rights reserved.

Fine Homebuilding receives a commission for items purchased through links on this site, including Amazon Associates and other affiliate advertising programs.

  • Home Group
  • Antique Trader
  • Arts & Crafts Homes
  • Bank Note Reporter
  • Cabin Life
  • Cuisine at Home
  • Fine Gardening
  • Fine Woodworking
  • Green Building Advisor
  • Garden Gate
  • Horticulture
  • Keep Craft Alive
  • Log Home Living
  • Military Trader/Vehicles
  • Numismatic News
  • Numismaster
  • Old Cars Weekly
  • Old House Journal
  • Period Homes
  • Popular Woodworking
  • Script
  • ShopNotes
  • Sports Collectors Digest
  • Threads
  • Timber Home Living
  • Traditional Building
  • Woodsmith
  • World Coin News
  • Writer's Digest
Active Interest Media logo
X
X
This is a dialog window which overlays the main content of the page. The modal window is a 'site map' of the most critical areas of the site. Pressing the Escape (ESC) button will close the modal and bring you back to where you were on the page.

Main Menu

  • How-To
  • Design
  • Tools & Materials
  • Video
  • Blogs
  • Forum
  • Project Guides
  • Reader Projects
  • Magazine
  • Members
  • FHB House

Podcasts

  • FHB Podcast
  • ProTalk

Webinars

  • Upcoming and On-Demand

Podcasts

  • FHB Podcast
  • ProTalk

Webinars

  • Upcoming and On-Demand

Popular Topics

  • Kitchens
  • Business
  • Bedrooms
  • Roofs
  • Architecture and Design
  • Green Building
  • Decks
  • Framing
  • Safety
  • Remodeling
  • Bathrooms
  • Windows
  • Tilework
  • Ceilings
  • HVAC

Magazine

  • Current Issue
  • Past Issues
  • Magazine Index
  • Subscribe
  • Online Archive
  • Author Guidelines

All Access

  • Member Home
  • Start Free Trial
  • Gift Membership

Online Learning

  • Courses
  • Project Guides
  • Reader Projects
  • Podcast

More

  • FHB Ambassadors
  • FHB House
  • Customer Support

Account

  • Log In
  • Join

Newsletter

Get home building tips, offers, and expert advice in your inbox

Signing you up...

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
See all newsletters
See all newsletters

Follow

  • X
  • YouTube
  • instagram
  • facebook
  • pinterest
  • Tiktok

Join All Access

Become a member and get instant access to thousands of videos, how-tos, tool reviews, and design features.

Start Your Free Trial

Subscribe

FHB Magazine

Start your subscription today and save up to 70%

Subscribe

Enjoy unlimited access to Fine Homebuilding. Join Now

Already a member? Log in

We hope you’ve enjoyed your free articles. To keep reading, become a member today.

Get complete site access to expert advice, how-to videos, Code Check, and more, plus the print magazine.

Start your FREE trial

Already a member? Log in

Privacy Policy Update

We use cookies, pixels, script and other tracking technologies to analyze and improve our service, to improve and personalize content, and for advertising to you. We also share information about your use of our site with third-party social media, advertising and analytics partners. You can view our Privacy Policy here and our Terms of Use here.

Cookies

Analytics

These cookies help us track site metrics to improve our sites and provide a better user experience.

Advertising/Social Media

These cookies are used to serve advertisements aligned with your interests.

Essential

These cookies are required to provide basic functions like page navigation and access to secure areas of the website.

Delete My Data

Delete all cookies and associated data