What’s the best way to sheath a hip roof? That is, how do you minimize waste and maximize speed?
Discussion Forum
Discussion Forum
Up Next
Video Shorts
Featured Story
Newer pressure treatments don't offer the same rot and decay resistance. Follow these simple strategies to give outdoor lumber its best chance of survival.
Featured Video
SawStop's Portable Tablesaw is Bigger and Better Than BeforeRelated Stories
Highlights
"I have learned so much thanks to the searchable articles on the FHB website. I can confidently say that I expect to be a life-long subscriber." - M.K.
Replies
*
What works for me is:
nail sheet's past hip...
chalk line....
cut.
Watch out for the saw dust up there.
*I like to cut on the ground using the sheathing cut factors in "Roof Framer's Bible".Say you have a 9/12 straight hip roof. The sheathing cut is 38-3/8". In other words, take your bottom measurement and deduct that for the top measurement. Provided the frame is accurate this method works great. With accurate cutting your sheathing will run true, straightening minor bends in the hip. Running the sheats long and cutting on the roof will do the same thing but I have never been able make it work for me on the steeper pitches we do.The great thing is it is really simple to get the bottom measurement, so you can put a less experienced guy on the roof. The book has cuts for all even pitches and most bastard hips you will find. I usually have to get a guy to do a roof or two before he get's on board with this method then they will be asking for the sheathing cuts as soon as we get on it.
*
*Thanks. Those are some good speed and safety tips, but is there any good way to minimize the waste of the off-cuts?
*I cannot handle 4x8 sheets on a roof alone so I use 2x8 sheets. I choose a pitch (8:12) and rafter center (16") that has little waste.I save the off cuts from the first row to start the second or third row. A bit of measuring will determine which is best.
*Charles, don't be too worried about waste. It'll work itself out, if you let it.Heres what I do. I start my bottom ply on the first or second rafter. I do all my cuts in place, no matter what pitch.On the hip, the ply will be hanging off. Immediately cut it along the hip. You'll notice that the piece will fit nicely on the remaing corner that you omitted. Recut this to fit and nail. When you get to the other side, there will be another "drop". If it fits nicely, use it. If not, save it. As you work your way up, every "drop" will find a home.At the end of the job, you will only have one "drop" left.blue