Although not an ‘official’ jobsite, I work as a carpenter & this is my biggest project to date…my own house.
So far:
- completely removed (flat) roof, framing & insulation
- replaced with 16″ TJI framing on 2-12 pitch
- removed all interior walls, elect & plumbing…I found lath & plaster walls & remnents of knob & tube electrical
- increased insulation from R7/R20 (walls/ceiling) to meet local requirements (R20/R40 walls/ceiling)
- new drywall. paint, cabnetry, plumbing fixtures, millwork, flooring
This short summary doesn’t begin to detail the headaches & creative problem solving required to get this project to it’s current state.